Yandi Sustaining Project - Materials Handling Infrastructure
The construction of Stacker 03 is part of Rio Tinto’s plan to further develop its current operations at Yandicoogina by increasing stockpile capacity and reliability. This machine was originally planned to be constructed in 2009, however was paused due to the looming global financial crisis.
Scope of Work
Goodline's scope consisted of the following:
- Refurbishment of the stored equipment
- Mechanical & Electrical erection of the YSK03 stacker to specification
- Pre Commissioning
- No Load Testing
- Load Testing & Commissioning
- Control System Checks
Client
Sandvik
Project Type
SMP & E&I
Year of Completion
2014
Project Location
Yandicoogina, WA